Large Load Additions

Connecting Large Energy Users While Protecting Reliability and Preventing Cost Shifting

Large energy users, such as data centers and advanced manufacturing facilities, are seeking to connect to the grid at an unprecedented pace and scale. Meeting that demand requires careful planning.

MISO has worked with utilities, regulators, large energy users and other stakeholders to develop a framework for supporting the reliable connection of large loads to the grid through faster studies, flexible service options, clear reliability requirements and greater transparency about who pays for grid upgrades.

In response to FERC's Large Load Show Cause Order, MISO also proposed tariff changes that build on existing planning processes and stakeholder input. Components addressing cost-shifting were filed jointly with transmission owners.

What MISO Is Proposing

  • Connect to the grid more quickly
    Expedited study options, including projects bringing new generation forward with demand while retaining necessary reliability reviews.
  • Protect customers and improve cost transparency
    Contracts and reporting that clarify cost responsibility, show upgrades driven by large loads and guard against cost shifting among wholesale transmission customers. Retail allocation and ratepayer protections remain within state jurisdiction.
  • Transition and grow with flexibility
    Service options that allow a large customer to begin or expand operations before all transmission upgrades are complete, provided the customer can reduce its electricity use when needed to protect grid reliability.
  • Protect reliability
    Clear requirements for data, forecasting, real-time visibility, operating coordination and how certain large loads must perform during grid disturbances.
  • Create a clear and efficient process
    A standardized application, defined study requirements and more consistent steps for evaluating large-load requests.

What's Next

FERC is reviewing MISO's proposed tariff changes. MISO will continue working with stakeholders to address any required proposal modifications and work on implementation plans for Q1 2027.

Transmission Photo

MISO is moving quickly to establish a framework through the Large Load Working Group. Your participation will help shape guidelines, processes, and solutions.