MISO members are seeing an unprecedented surge in large load interconnection requests, driven by data centers, advanced manufacturing, AI computing facilities and other energy-intensive industries. These projects are reshaping the grid in both scale and speed, with many seeking to connect within 18–36 months, far faster than traditional generation and transmission build timelines.
Underscoring the need to support these fast-growing loads, on June 18, 2026, FERC directed all RTOs/ISOs, including MISO, to update large load tariff provisions (195 FERC ¶ 61,212) to demonstrate that existing and planned approaches adequately support large load interconnection.
To keep pace, we’ve already accelerated interconnection and transmission solutions through Expedited Resource Addition Study (ERAS) and MTEP's Expedited Project Review (EPR). Now, MISO is executing on a three-part framework that we believe is directionally consistent with FERC’s order.
1. Connect quickly: Large loads can get MISO approval within 120 days with all studies and GIAs signed.
2. Transition and scale with flexibility: Large loads can transition and scale with flexible options consistent with timing of network upgrade buildouts.
3. Operate with long-term reliability: Large loads sustain reliable operations with the ability to withdraw or inject energy based on conditions and signals.

MISO is moving quickly to establish a framework through the Large Load Working Group. Your participation will help shape guidelines, processes, and solutions.